Start with something familiar
Two recipes may use the same oven but very different amounts of preparation time. Baking only the quick recipe can make oven capacity look generous while the cook struggles. A mixed menu needs a resource table rather than one average cooking time. Northstar faces the same issue when a plain bottle and a decorated bottle share equipment. Changing the mix changes which resource fills first, even when the total number of bottles is unchanged.
Words to know: Bottleneck, Load, Objective.
Understand the constraint
Call the plain bottle A and the decorated bottle B. A uses ten machine minutes and six labor minutes. B uses twenty machine minutes and four labor minutes. The shift supplies two hundred machine minutes and one hundred twenty labor minutes. With demand caps of twelve A and ten B, a proposed mix of twelve A and four B uses all two hundred machine minutes but only eighty eight labor minutes. That mix is feasible. The machine is binding while labor has thirty two minutes of headroom.
Now compare ten A and five B. Machine load remains two hundred minutes, while labor falls to eighty minutes. Equal machine load does not imply equal product counts or value. If contribution is six currency units per A and fourteen per B, twelve A plus four B contributes one hundred twenty eight, while ten A plus five B contributes one hundred thirty. This value comparison assumes contribution already subtracts the relevant variable costs. It says nothing by itself about promised customer service.
Interpret the result
A single average time is risky when the product mix moves. Fifteen A need one hundred fifty machine minutes and ninety labor minutes; fifteen B need three hundred machine minutes and sixty labor minutes. Both are fifteen bottles but have very different feasibility. Resource use per product should remain visible in the model. Contribution per bottleneck minute can guide a simple one-resource comparison, but it does not replace checking all constraints, product demand caps, or a policy that protects a minimum allocation.
Create one row for each resource or stock position and one column for each time bucket. Put the unit in the row label and keep inputs separate from calculated results. Begin with the smallest case you can verify by hand, then extend the same equations across periods. Give every receipt a usable date and every requirement a due date. Preserve the baseline before changing an assumption so the effect of an action is visible.
Validate and explain
Use a second check that follows the physical story. Count what enters, what is used, what waits, and what leaves. A plan that balances in total can still fail at an earlier cutoff. Mark any unavailable input as an assumption rather than filling it with a convenient zero. A zero means a known absence; an unknown value means the promise remains conditional. This difference belongs in both the model and the decision note.
A calculation becomes useful when it changes a choice. Compare the baseline with at least two scenarios, identify the first limiting condition in each, and explain what additional resource would actually change delivered output. Keep a service measure alongside any cost or value measure. State whether the choice maximizes value, protects a commitment, or reduces the worst shortfall. A different goal can produce a different sensible answer from the same facts. Finish by testing one deliberately wrong proposal, such as a receipt used before arrival or a quantity above a resource ceiling. Your table should make that error visible. Save the rejected proposal with a short explanation, because it teaches a reviewer how the checks work. The eight hours include rebuilding, scenario work, writing, and teach-back; they are self-paced estimates rather than measured completion times. Faster readers should deepen the checks instead of merely rereading the text.
- Define units and dates
- Calculate required use
- Check every limit
- Compare actions
- Release a conditional plan
Northstar: product mix and changing resource pressure
All quantities below are fictional and apply only to this fully specified exercise. Monetary values are generic currency units.
| Product | Machine minutes/unit | Labor minutes/unit | Contribution/unit | Demand cap |
|---|---|---|---|---|
| A | 10 | 6 | 6 | 12 |
| B | 20 | 4 | 14 | 10 |
- 1. 12 A + 4 B uses 120 + 80 = 200 machine minutes.
- 2. Labor is 72 + 16 = 88 minutes.
- 3. Contribution is 72 + 56 = 128 currency units.
The example mix is feasible and leaves 32 labor minutes.
Assumptions
- All unlisted resource restrictions are absent for this teaching case.
- Use the timing, yield, and carry rules stated in the lesson; do not add unstated receipts.
Where this can fail: This model is conditional on its supplied inputs. It does not certify supplier execution, actual yield, or a detailed shop-floor sequence.
Build, test and explain a plan
Use the stated A/B data for three shifts, each with machine capacity 200 and labor capacity 120. Demand caps per shift remain A12/B10 with no carry. Evaluate mixes 12/4, 10/5, and 0/10 in every shift. Then reduce labor to 70 in shift two and machine time to 180 in shift three. Add a service requirement of at least six A per shift and find a feasible integer mix for each shift. The eight-hour estimate covers an original workbook or paper model, scenario calculations, checks, and communication; it is not experimentally validated.
Use paper or a spreadsheet. The estimates below include the study and worked example already on this page.
| Estimated hours | Activity |
|---|---|
| 0.5 | Study the two constraint explanations. Write a data dictionary with units, dates, and the boundary of each resource. |
| 0.5 | Recalculate the worked example without looking at its answer. Reconcile every difference and record the corrected arithmetic. |
| 3 | Build the complete multi-period or multi-case planning table specified above. Keep inputs separate, show all formulas, and add explicit checks for capacity, stock, and due quantities. |
| 2 | Run every requested stress case. Add a comparison table of resource use, feasible output, remaining gaps, and the first constraint that blocks improvement. |
| 1 | Write a one-page decision memo that selects a feasible action, states its goal, names the assumptions, and distinguishes firm results from conditional ones. |
| 1 | Teach the model aloud to an imagined colleague. Trace one bottle or one decision through all rows, test one invalid proposal, and revise unclear labels. |
Your deliverables
- A reproducible planning table with inputs, formulas, units, and checks.
- A scenario comparison with service and resource consequences.
- A decision memo and short teach-back outline.
Check your practice work
- Mixes 12/4, 10/5, 0/10 yield contributions 128, 130, 140 and labor 88,80,40.
- At labor 70, mix 6/7 is feasible: machine 200, labor 64, contribution 134.
- At machine 180 and minimum A6, mix 6/6 is feasible: machine 180, labor 60, contribution 120.
Keep these three ideas
- Compare products using their actual resource requirements.
- Keep quantities, resource units, and due times explicit.
- Recheck all constraints after a change, and report remaining uncertainty.
Common mistakes
- Treating capacity in a later time bucket as available before the due gate.
- Calling an expected or conditional quantity a guaranteed shipment.
Optional video study
Compare products using their actual resource requirements.
- Frame the Northstar constraint and unit.
- Walk the checked example through every resource.
- Compare the lab stress cases and explain the release decision.
The second half of the module narration uses this lesson’s case and checks.
Open the module media & quizPut this idea to use