Lead times and replenishment policies
Translate usable dates into releases and choose explicit review rules.
Separate procurement, transit, inspection, and working calendars.
LESSON 2 · 8-HOUR ACTIVITY PLANChoose continuous or periodic reviewCalculate order triggers and order-up-to quantities using a consistent inventory position.
Watch, listen or read
Translate usable dates into releases and choose explicit review rules.
5:00 · Original narrated lesson slides. AI-generated narration through Runway; factual diagrams assembled for this course. Video is optional. The complete transcript is directly below.
Read the complete narration transcript
A supply order has two dates that must not be mixed up. One is when we release it. The other is when its goods can be used. Between those dates, work must happen. Northstar needs a part ready at the start of working day ten. The source needs two days. Travel needs one day. The receipt check needs one day. Those steps are in a row, so the total is four working days.
Under our start of day rule, release at the start of day six. Four days later is the start of day ten. This sounds easy because we have made the clock clear. In real work, ask when the first step starts. If a source begins only the day after release, the result changes. If the truck runs on Sunday but the store is shut, the last step must use a different calendar. A date without a calendar can give false comfort.
Suppose the order cannot be released until day eight. With four days of lead time, it will be usable on day twelve. That is two working days late. Moving a cell to day ten does not make the goods move faster. The plan needs a real choice. We might get a firm faster route, use an approved source, split the shipment, or agree a later date. Each choice needs a cost, an owner, and proof.
A mean lead time is useful, but it is not the same as a firm date for this order. Keep the normal time, the current promise, and the actual time apart. Then we can learn what went wrong. Was the standard out of date? Was this one order held? Was the truck late? Did the check take longer? A clear record points to a useful fix.
Now turn from dates to the rule for when to buy. We will use inventory position. In this lesson it means stock on hand plus open supply less backlog. Northstar has twenty on hand, thirty on order, and five still owed. Its position is forty five. That does not mean forty five can ship now. Some of it is still on the way. We still need the date view to protect today's demand.
One policy checks the position after each event. Mean demand is ten a day. Lead time is three days. Mean need while we wait is thirty. Add a buffer of ten and the reorder point is forty. Our stated rule orders a fixed lot when position is at or below forty. At forty five, it does not yet order. The equality rule matters. Put it in the policy so two people get the same answer.
A second policy checks only every four days. It must cover the time until the next check as well as lead time. Four plus three is seven days. At ten a day, that is seventy. Add the stated ten unit buffer and the target is eighty. At position forty five, the new order is thirty five. We buy the gap to the target, not the full target each time.
For this example we kept the buffer fixed to show the role of review time. In a full risk model, a longer wait may need more buffer too. If goods come in packs of twelve, thirty five rounds up to thirty six. The new position becomes eighty one. Note the extra unit rather than hiding it in the formula.
When the thirty already on order arrives, move it from open supply to stock. Position does not jump just because a receipt changes status. That is a useful check. In the lab, follow daily demand, receipts, stock, position, and new orders for both rules. Keep the base case, then test a demand spike and a longer lead time. See which event first puts service at risk.
The final choice is not just a formula. It is a rule that a buyer can use and a team can check. State the review day, the lead calendar, the lot size, the trigger, and the path for an urgent exception. Then connect the rule back to the dates on which customers need the goods.
As a last check, say what changes if the receipt check takes one more day. The release must move one day earlier to hold the same usable date. If it cannot move, show the later date and the demand at risk.
Video teaching plan
- Work backward
Four sequential day blocks end at day ten
- 2 source
- 1 transit
- 1 check
- Past release
Required and feasible date lanes
- Release day 6
- Late release 8
- Usable day 12
- Position
Three arithmetic cards form position forty-five
- 20 on hand
- 30 open
- 5 backlog
- Continuous rule
Position marker against forty trigger
- Daily events
- Point 40
- Fixed lot
- Periodic rule
Seven-day protection bracket
- Review 4
- Lead 3
- Target 80
- Policy trial
Two twelve-day stock paths
- Keep base
- Test spike
- Check dates
Module practice & recap
Northstar checks inventory every four days. Lead time is three working days, mean demand ten/day, and stipulated buffer ten. Position at review is 45, consisting of 20 stock,30 open supply, and 5 backlog. The open supply is usable tomorrow. The next review is four days away. All days are working days. Suggested time: one hour model and checks, one hour scenarios, one hour memo and peer-style review; estimates are not experimentally validated.
- Compute continuous reorder point and periodic target under the given buffer.
- Compute a periodic order with pack size twelve and show the resulting position.
- Date that order from start day 6 to usable start day 9; compare a one-day inspection delay.
- Explain why inventory position cannot prove all five backlog units can ship immediately.
What to produce
- A reconciled scenario table with formulas and units.
- A short decision memo with service, cost, and risk implications.
- An assumption and exception register with owners and review dates.
Ordinary practice answer checks
- Continuous point 40; periodic target 80.
- Order 35 unrounded or 36 in packs; resulting position 81.
- Four-day lead makes usable receipt day 10; existing on-hand 20 is enough for backlog 5 but other immediate requirements must be checked.
10 quick questions
Choose an answer, then check it. Retry any question without penalty. The one-hour budget includes checking, revisiting examples, and explaining your choices.
0 of 10 answered · 0 correct