WORKED SUPPLY CHAIN EXAMPLE · SCI-007 · CONSUMER HARDWARE

Example SCI-007: Two materials one finishing partner — Both suppliers outsource final finishing.

What goes wrong: A finishing stoppage blocks both nominally available sources. How we fix it: Preposition the specified A and B buffers before the event.

Everyday Real-Life Example: Common mistake: thinking "Independent supplier names imply independent recovery." In reality: Two primary sources depend on one failed resource.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-007)

Bar chart comparing normal day, problem day, and fixed plan for SCI-007

Key Question to Ask: Trace the final process before an item becomes shippable.

How to Fix It: Preposition the specified A and B buffers before the event.

Simple Summary of This Example

Starting Numbers & Units for SCI-007

Starting Numbers and Allowed Ranges (SCI-007)
Number Name Unit of Measure Starting Value Allowed Range
demand kits (demand_kits) complete kits 100 0 to 10000 (integer)
primary a (primary_a) pieces 100 0 to 1000000 (integer)
primary b (primary_b) pieces 100 0 to 1000000 (integer)
backup capacity (backup_capacity) pieces 160 0 to 1000000 (integer)
buffer a (buffer_a) pieces 20 0 to 1000000 (integer)
buffer b (buffer_b) pieces 20 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-007)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
on time kits (on_time_kits) complete kits 100 80 100
late kits (late_kits) complete kits 0 20 0
backup a (backup_a) pieces 0 80 80
backup b (backup_b) pieces 0 80 80