EASY SUPPLY CHAIN CONCEPT #3 OF 16

Sharing One Busy Machine Between Fast and Slow Products

When two products share one machine and Product A is always made first, any machine breakdown time comes 100% out of Product B.

Everyday Real-Life Example: If you have 8 hours in a kitchen and always bake Cakes first (3 hours) and Cookies second (5 hours), losing 2 hours of oven time means Cakes still finish 100%, while Cookies get cut.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

How This Rule Works in Simple Steps

What We Want to Achieve: honor the declared A-first policy — Different products consume different minutes on one resource.

Three Simple Steps We Compare on This Page

Important Things to Remember Before Using in Real Life

7 Worked Examples of "Sharing One Busy Machine Between Fast and Slow Products"

Click any of the 7 worked examples below to open its own separate page with step-by-step numbers and a visual bar chart: