How Running Batch B Before Batch A Saves Cleaning Time and Prevents Overtime
Switching a machine from dark-colored Batch A to light-colored Batch B takes 110 minutes of deep cleaning, whereas running light Batch B first and dark Batch A second takes only 50 minutes.
Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.
How This Rule Works in Simple Steps
What We Want to Achieve: complete both batches within shift — The order of two batches changes the time needed.
- Total minutes = run minutes A + run minutes B + changeover.
- Sequence changes do not create extra processing capacity.
- A faster sequence still fails if total exceeds the shift.
- Keep pure calculation code separate from storage and UI.
Three Simple Steps We Compare on This Page
- 1. Normal Day (Baseline Plan): Apply the baseline policy to the frozen input state.
- 2. Problem Day (When Something Goes Wrong): Apply the actual A-to-B changeover to the planned sequence.
- 3. Fixed Plan (How We Solve It): Use the allowed reverse sequence and its documented changeover.
Important Things to Remember Before Using in Real Life
- Both batches have the same due time; order reversal is permitted.
- Passing this model does not validate a complete real supply chain.
- A case must disclose every assumption used in the calculation.
7 Worked Examples of "How Running Batch B Before Batch A Saves Cleaning Time and Prevents Overtime"
Click any of the 7 worked examples below to open its own separate page with step-by-step numbers and a visual bar chart:
- SCI-099: A to B is not B to A — The two changeover directions take different times. (A reverse sequence can reduce time without changing demand.)
- SCI-100: Cleaning direction matters — The permitted product sequence changes cleaning effort. (The toy assumes both sequences are operationally allowed.)
- SCI-101: Tool change direction — Changing tools in the two directions takes different time. (An average setup can hide an overtime requirement.)
- SCI-102: Shared due time permits reversal — Both batches share the same final due time. (Sequence improvement depends on the stated due-date flexibility.)
- SCI-103: A fast setup still insufficient — A shorter changeover may still leave overtime. (A locally better action is not automatically a feasible plan.)
- SCI-104: Maintenance placed between batches — The scenario represents extra time between batches. (The simplified time model must not double-count the same interval.)
- SCI-105: Changeover knowledge captured — An operator explains the directional setup difference. (A useful finding preserves the assumption for the next planning cycle.)