Supply Chain Ideas Simple, Clear Supply Chain Learning for Everyone
WORKED SUPPLY CHAIN EXAMPLE · SCI-102 · OFFICE MANUFACTURING

Example SCI-102: Shared due time permits reversal — Both batches share the same final due time.

What goes wrong: Sequence improvement depends on the stated due-date flexibility. How we fix it: Use the allowed reverse sequence and its documented changeover.

Everyday Real-Life Example: Common mistake: thinking "Changeover time is symmetric between product families." In reality: The order of two batches changes the time needed.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-102)

Bar chart comparing normal day, problem day, and fixed plan for SCI-102

Key Question to Ask: Verify that reversing order does not violate an earlier promise.

How to Fix It: Use the allowed reverse sequence and its documented changeover.

Simple Summary of This Example

Starting Numbers & Units for SCI-102

Starting Numbers and Allowed Ranges (SCI-102)
Number Name Unit of Measure Starting Value Allowed Range
units a (units_a) pieces 80 0 to 1000000 (integer)
units b (units_b) pieces 60 0 to 1000000 (integer)
time a (time_a) minutes per unit 2 0 to 1000000 (integer)
time b (time_b) minutes per unit 3 0 to 1000000 (integer)
shift minutes (shift_minutes) minutes 420 0 to 1000000 (integer)
assumed setup (assumed_setup) minutes 30 0 to 1000000 (integer)
a to b setup (a_to_b_setup) minutes 110 0 to 1000000 (integer)
b to a setup (b_to_a_setup) minutes 50 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-102)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
process minutes (process_minutes) minutes 340 340 340
setup minutes (setup_minutes) minutes 30 110 50
total minutes (total_minutes) minutes 370 450 390
overtime minutes (overtime_minutes) minutes 0 30 0

Other Related Examples on "How Running Batch B Before Batch A Saves Cleaning Time and Prevents Overtime"