WORKED SUPPLY CHAIN EXAMPLE · SCI-103 · ASSEMBLY FINISHING

Example SCI-103: A fast setup still insufficient — A shorter changeover may still leave overtime.

What goes wrong: A locally better action is not automatically a feasible plan. How we fix it: Use the allowed reverse sequence and its documented changeover.

Everyday Real-Life Example: Common mistake: thinking "Changeover time is symmetric between product families." In reality: The order of two batches changes the time needed.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-103)

Bar chart comparing normal day, problem day, and fixed plan for SCI-103

Key Question to Ask: Compare the full run plus setup time with the shift.

How to Fix It: Use the allowed reverse sequence and its documented changeover.

Simple Summary of This Example

Starting Numbers & Units for SCI-103

Starting Numbers and Allowed Ranges (SCI-103)
Number Name Unit of Measure Starting Value Allowed Range
units a (units_a) pieces 80 0 to 1000000 (integer)
units b (units_b) pieces 60 0 to 1000000 (integer)
time a (time_a) minutes per unit 2 0 to 1000000 (integer)
time b (time_b) minutes per unit 3 0 to 1000000 (integer)
shift minutes (shift_minutes) minutes 370 0 to 1000000 (integer)
assumed setup (assumed_setup) minutes 30 0 to 1000000 (integer)
a to b setup (a_to_b_setup) minutes 110 0 to 1000000 (integer)
b to a setup (b_to_a_setup) minutes 50 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-103)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
process minutes (process_minutes) minutes 340 340 340
setup minutes (setup_minutes) minutes 30 110 50
total minutes (total_minutes) minutes 370 450 390
overtime minutes (overtime_minutes) minutes 0 80 20

Other Related Examples on "How Running Batch B Before Batch A Saves Cleaning Time and Prevents Overtime"