Example SCI-021: Shared cleaning crew — One crew performs both product-specific tasks.
What goes wrong: Parallel equipment does not imply parallel qualified service. How we fix it: Add only approved extra minutes to the same constrained resource.
Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.
Visual Before-and-After Chart (SCI-021)
Key Question to Ask: Inspect crew work minutes across both production families.
How to Fix It: Add only approved extra minutes to the same constrained resource.
Simple Summary of This Example
- Example Number:
SCI-021(reusable containers) - Plain-English Topic: Sharing One Busy Machine Between Fast and Slow Products
- Main Goal: honor the declared A-first policy
- Important Limit: Fixed priority A then B; no sequence setup in this model.
Starting Numbers & Units for SCI-021
| Number Name | Unit of Measure | Starting Value | Allowed Range |
|---|---|---|---|
demand a (demand_a) |
pieces | 60 | 0 to 1000000 (integer) |
demand b (demand_b) |
pieces | 50 | 0 to 1000000 (integer) |
minutes a (minutes_a) |
minutes per unit | 3 | 1 to 1000000 (integer) |
minutes b (minutes_b) |
minutes per unit | 6 | 1 to 1000000 (integer) |
capacity minutes (capacity_minutes) |
minutes | 480 | 0 to 1000000 (integer) |
lost minutes (lost_minutes) |
minutes | 60 | 0 to 1000000 (integer) |
extra minutes (extra_minutes) |
minutes | 60 | 0 to 1000000 (integer) |
Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-021)
| Result Name | Unit | Normal Day (Baseline) | Problem Day (Stress) | Fixed Plan (Repair) |
|---|---|---|---|---|
units a (units_a) |
pieces | 60 | 60 | 60 |
units b (units_b) |
pieces | 50 | 40 | 50 |
total late (total_late) |
pieces | 0 | 10 | 0 |
minutes used (minutes_used) |
minutes | 480 | 420 | 480 |
Other Related Examples on "Sharing One Busy Machine Between Fast and Slow Products"
- SCI-015: The unit capacity shortcut — Product B uses twice the resource time.
- SCI-016: One operator two stations — Two stations require the same qualified operator.
- SCI-017: Shared final test — Two products compete for one final tester.
- SCI-018: Shortened production shift — A planned maintenance task reduces shift minutes.
- SCI-019: Priority consumes recovery — Urgent A units receive the fixed first priority.
- SCI-020: Training consumes qualified time — Only qualified worker minutes count.
- SCI-021: Shared cleaning crew (This Page)