Supply Chain Ideas Simple, Clear Supply Chain Learning for Everyone
WORKED SUPPLY CHAIN EXAMPLE · SCI-055 · OFFICE FURNITURE

Example SCI-055: Month boundary and weekend — A planning period boundary falls over a weekend.

What goes wrong: An ordinal-day toy exposes the boundary effect without timezone ambiguity. How we fix it: Release on the explicitly approved earlier ordinal day.

Everyday Real-Life Example: Common mistake: thinking "Working-day lead time can always be added as calendar days." In reality: A nonworking day changes the feasible availability date.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-055)

Bar chart comparing normal day, problem day, and fixed plan for SCI-055

Key Question to Ask: Calculate actual working days rather than assuming equal periods.

How to Fix It: Release on the explicitly approved earlier ordinal day.

Simple Summary of This Example

Starting Numbers & Units for SCI-055

Starting Numbers and Allowed Ranges (SCI-055)
Number Name Unit of Measure Starting Value Allowed Range
release day (release_day) ordinal calendar day with day one Monday 5 0 to 1000000 (integer)
lead workdays (lead_workdays) working days excluding release day 2 0 to 1000000 (integer)
due day (due_day) ordinal calendar day with day one Monday 9 0 to 1000000 (integer)
holiday day (holiday_day) ordinal calendar day with day one Monday 8 0 to 1000000 (integer)
early release day (early_release_day) ordinal calendar day with day one Monday 4 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-055)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
ready day (ready_day) ordinal calendar day with day one Monday 9 10 9
days late (days_late) calendar days 0 1 0
on time (on_time) one for true zero for false 1 0 1

Other Related Examples on "Why Weekends and Supplier Holidays Push Delivery Dates Past the Deadline"