Supply Chain Ideas Simple, Clear Supply Chain Learning for Everyone
WORKED SUPPLY CHAIN EXAMPLE · SCI-062 · RURAL DISTRIBUTION

Example SCI-062: Remote delivery schedule — Service operates on a sparse published schedule.

What goes wrong: Average transit time hides the waiting time before departure. How we fix it: Use an explicitly prearranged recovery departure.

Everyday Real-Life Example: Common mistake: thinking "One day of readiness delay means one day of delivery delay." In reality: A small readiness delay misses a discrete transport departure.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-062)

Bar chart comparing normal day, problem day, and fixed plan for SCI-062

Key Question to Ask: Use the service calendar rather than an average transit duration.

How to Fix It: Use an explicitly prearranged recovery departure.

Simple Summary of This Example

Starting Numbers & Units for SCI-062

Starting Numbers and Allowed Ranges (SCI-062)
Number Name Unit of Measure Starting Value Allowed Range
ready day (ready_day) ordinal calendar day with day one Monday 2 0 to 1000000 (integer)
delay days (delay_days) calendar days 1 0 to 1000000 (integer)
departure one (departure_one) ordinal calendar day with day one Monday 3 0 to 1000000 (integer)
departure two (departure_two) ordinal calendar day with day one Monday 10 0 to 1000000 (integer)
cutoff gap (cutoff_gap) calendar days 1 0 to 1000000 (integer)
transit days (transit_days) calendar days 2 0 to 1000000 (integer)
due day (due_day) ordinal calendar day with day one Monday 6 0 to 1000000 (integer)
recovery departure (recovery_departure) ordinal calendar day with day one Monday 4 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-062)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
departure day (departure_day) ordinal calendar day with day one Monday 3 10 4
arrival day (arrival_day) ordinal calendar day with day one Monday 5 12 6
days late (days_late) calendar days 0 6 0
on time (on_time) one for true zero for false 1 0 1

Other Related Examples on "Why a 1-Day Factory Delay Causes a 7-Day Shipping Delay When You Miss Cutoff"