Supply Chain Ideas Simple, Clear Supply Chain Learning for Everyone
WORKED SUPPLY CHAIN EXAMPLE · SCI-079 · PRODUCT LAUNCH

Example SCI-079: Reserved launch stock — A launch allocation protects part of the stock.

What goes wrong: A new order cannot silently consume launch stock. How we fix it: Release only the quantity explicitly approved as usable.

Everyday Real-Life Example: Common mistake: thinking "Every physical unit is available to a new order." In reality: Reserved and quarantined quantities reduce usable stock.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-079)

Bar chart comparing normal day, problem day, and fixed plan for SCI-079

Key Question to Ask: Check the authority needed to change the protected allocation.

How to Fix It: Release only the quantity explicitly approved as usable.

Simple Summary of This Example

Starting Numbers & Units for SCI-079

Starting Numbers and Allowed Ranges (SCI-079)
Number Name Unit of Measure Starting Value Allowed Range
gross stock (gross_stock) pieces 300 0 to 1000000 (integer)
reserved stock (reserved_stock) pieces 120 0 to 1000000 (integer)
quarantined stock (quarantined_stock) pieces 60 0 to 1000000 (integer)
new demand (new_demand) pieces 150 0 to 1000000 (integer)
approved release (approved_release) pieces 60 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-079)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
usable units (usable_units) pieces 300 120 180
on time units (on_time_units) pieces 150 120 150
late units (late_units) pieces 0 30 0
remaining usable (remaining_usable) pieces 150 0 30

Other Related Examples on "Why Warehouse Stock on the Floor Is Not the Same as Stock You Can Sell"