Start with something familiar
A relay runner cannot help by shouting that the team is fast enough. The next runner needs a clear handover point and must know when to start. Planning has its own handover. Procurement, production, inspection, and transport need the same approved quantity and time, plus a rule for what to do when an assumption fails. A detailed table without that agreement can still create conflicting actions on the day.
Words to know: Trigger, Scenario, Finite capacity.
Understand the constraint
A decision record should separate known facts, assumptions, choices, and triggers. For Northstar the requirement is twenty nine good bottles. The current supplier ceiling is twenty four. A proposed five-unit recovery is not confirmed until procurement verifies availability and arrival before the production release gate. Manufacturing has a ceiling of thirty two and transport thirty in this simplified good-unit model. Record the version and time of each confirmation. A later change in a hard constraint should reopen the decision rather than silently replace a cell.
Use concrete checkpoints. Procurement must confirm the five extra equivalents by Monday at ten. If confirmation fails, the planner reduces the firm new-flow promise to twenty four and records five unfilled units. If confirmation succeeds but the carrier later confirms only twenty seven slots, transport activates a pre-reserved three-slot backup by Tuesday noon. These actions are fictional operating rules for this case. They require named roles, stated deadlines, and authority; a vague instruction to expedite does not tell a colleague what to do.
Interpret the result
The final handoff contains the quantities to start, quantities expected good, quantities approved to ship, and the checks that connect them. Do not mix the good-unit capacity example with a separate yield-based start calculation without translating the units. In a physical run with a ninety seven percent expected yield, thirty starts support an expectation of twenty nine point one good bottles, not a firm guarantee of twenty nine. Inspection should release actual good stock, and customer service should update the promise if the released amount misses the committed quantity.
Create one row for each resource or stock position and one column for each time bucket. Put the unit in the row label and keep inputs separate from calculated results. Begin with the smallest case you can verify by hand, then extend the same equations across periods. Give every receipt a usable date and every requirement a due date. Preserve the baseline before changing an assumption so the effect of an action is visible.
Validate and explain
Use a second check that follows the physical story. Count what enters, what is used, what waits, and what leaves. A plan that balances in total can still fail at an earlier cutoff. Mark any unavailable input as an assumption rather than filling it with a convenient zero. A zero means a known absence; an unknown value means the promise remains conditional. This difference belongs in both the model and the decision note.
A calculation becomes useful when it changes a choice. Compare the baseline with at least two scenarios, identify the first limiting condition in each, and explain what additional resource would actually change delivered output. Keep a service measure alongside any cost or value measure. State whether the choice maximizes value, protects a commitment, or reduces the worst shortfall. A different goal can produce a different sensible answer from the same facts. Finish by testing one deliberately wrong proposal, such as a receipt used before arrival or a quantity above a resource ceiling. Your table should make that error visible. Save the rejected proposal with a short explanation, because it teaches a reviewer how the checks work. The eight hours include rebuilding, scenario work, writing, and teach-back; they are self-paced estimates rather than measured completion times. Faster readers should deepen the checks instead of merely rereading the text.
- Define units and dates
- Calculate required use
- Check every limit
- Compare actions
- Release a conditional plan
Northstar: decision handoff and trigger control
All quantities below are fictional and apply only to this fully specified exercise. Monetary values are generic currency units.
| Item | Value or limit | Unit or context |
|---|---|---|
| Procurement confirmation | Monday 10:00 | 5 extra equivalents |
| Carrier confirmation | Tuesday 10:00 | at least 29 slots |
| Backup activation | Tuesday 12:00 | 3 reserved slots |
| Inspection release | Before loading | actual good quantity |
- 1. If supply is unconfirmed, firm baseline flow stays min(24,32,30)=24.
- 2. If supply is 29 but shipping is 27, nominal gap is 2.
- 3. Activating three reserved slots yields min(29,32,30)=29.
An executable handoff binds each promised quantity to a verified gate and an authorized owner.
Assumptions
- All unlisted resource restrictions are absent for this teaching case.
- Use the timing, yield, and carry rules stated in the lesson; do not add unstated receipts.
Where this can fail: This model is conditional on its supplied inputs. It does not certify supplier execution, actual yield, or a detailed shop-floor sequence.
Build, test and explain a plan
Create a three-checkpoint decision log for Monday10:00, Tuesday10:00, and Tuesday12:00. Test three paths: supply confirmed and carrier30; supply confirmed and carrier27 with available backup; supply not confirmed and carrier30. Initial ceilings are 24/32/30 and need29. Backup adds3 slots, only when activated by Tuesday noon. Add a late message arriving Tuesday13:00 and explain what can no longer be assumed. Write one release note per path. The eight-hour estimate covers an original workbook or paper model, scenario calculations, checks, and communication; it is not experimentally validated.
Use paper or a spreadsheet. The estimates below include the study and worked example already on this page.
| Estimated hours | Activity |
|---|---|
| 0.5 | Study the two constraint explanations. Write a data dictionary with units, dates, and the boundary of each resource. |
| 0.5 | Recalculate the worked example without looking at its answer. Reconcile every difference and record the corrected arithmetic. |
| 3 | Build the complete multi-period or multi-case planning table specified above. Keep inputs separate, show all formulas, and add explicit checks for capacity, stock, and due quantities. |
| 2 | Run every requested stress case. Add a comparison table of resource use, feasible output, remaining gaps, and the first constraint that blocks improvement. |
| 1 | Write a one-page decision memo that selects a feasible action, states its goal, names the assumptions, and distinguishes firm results from conditional ones. |
| 1 | Teach the model aloud to an imagined colleague. Trace one bottle or one decision through all rows, test one invalid proposal, and revise unclear labels. |
Your deliverables
- A reproducible planning table with inputs, formulas, units, and checks.
- A scenario comparison with service and resource consequences.
- A decision memo and short teach-back outline.
Check your practice work
- Confirmed supply and carrier30 support firm flow29 if inspection also releases enough good bottles.
- Confirmed supply and carrier27 require backup activation before noon to restore nominal flow29.
- Unconfirmed extra supply supports only24 and leaves5 unmet; extra truck slots cannot close a material gap.
- A 13:00 message misses the backup deadline, so guaranteed access must not be assumed; escalate the remaining gap with evidence.
Keep these three ideas
- Turn a conditional model into an executable promise with owners.
- Keep quantities, resource units, and due times explicit.
- Recheck all constraints after a change, and report remaining uncertainty.
Common mistakes
- Treating capacity in a later time bucket as available before the due gate.
- Calling an expected or conditional quantity a guaranteed shipment.
Optional video study
Turn a conditional model into an executable promise with owners.
- Frame the Northstar constraint and unit.
- Walk the checked example through every resource.
- Compare the lab stress cases and explain the release decision.
The second half of the module narration uses this lesson’s case and checks.
Open the module media & quizPut this idea to use
Carry your assumptions into a practical tool, then compare your result with a short guide.
Open a related planning toolRead the related planning guidePractice with the planning gameThis saves a completion marker in this browser only. It does not verify time spent.