8-HOUR STUDY & PRACTICE PLAN · TEXT ABOUT 20 MINUTES

Recovery scenarios and uncertainty

Evaluate recovery as a chain of contingent effects.

The hours include the activities below, not just reading this page. Work at your own pace.

Start with something familiar

A spare umbrella helps only if it is where you are when rain begins. Buying another one at home does little if you are already at the station. Recovery plans have the same timing problem. An extra supply order may be useful, late, or blocked by the next stage. A good plan names the event that makes the option useful and keeps uncertain arrivals separate from confirmed stock.

Understand the constraint

Return to the common Northstar requirement of twenty nine good bottles. Supplier, manufacturing, and shipping ceilings are twenty four, thirty two, and thirty. Buying five additional on-time supplier equivalents for ten currency units each closes the nominal gap and costs fifty. Buying eight equivalents costs eighty but permits only thirty shipments because shipping becomes limiting. Against the twenty nine requirement, the extra three units beyond the needed five do not improve current due service. They might have later value, but that is a separate decision.

Now consider a downside case in which shipping falls to twenty seven. With the five-unit supplier recovery, completed flow is min(29,32,27), or twenty seven, leaving two late. A backup carrier can add three shipping slots for a fixed fee of eighteen, restoring the needed flow to twenty nine. An action should be checked against all downstream gates and should be charged according to its actual cost rule. Fixed fees differ from per-unit costs. Do not multiply a fixed pickup fee by the number of bottles.

Interpret the result

Without probabilities, compare scenarios without claiming an expected cost. If a decision maker supplies explicit probabilities, a weighted result can be calculated, but that does not guarantee a particular outcome. For teaching, use a sixty percent nominal case and forty percent shipping-downside case, and treat these probabilities as assumptions. Supplier recovery alone yields weighted shortfall of point eight bottle, although actual shortfall is either zero or two. Paying for contingent backup only in the downside has expected added fee seven point two, assuming activation is reliably available.

Create one row for each resource or stock position and one column for each time bucket. Put the unit in the row label and keep inputs separate from calculated results. Begin with the smallest case you can verify by hand, then extend the same equations across periods. Give every receipt a usable date and every requirement a due date. Preserve the baseline before changing an assumption so the effect of an action is visible.

Validate and explain

Use a second check that follows the physical story. Count what enters, what is used, what waits, and what leaves. A plan that balances in total can still fail at an earlier cutoff. Mark any unavailable input as an assumption rather than filling it with a convenient zero. A zero means a known absence; an unknown value means the promise remains conditional. This difference belongs in both the model and the decision note.

A calculation becomes useful when it changes a choice. Compare the baseline with at least two scenarios, identify the first limiting condition in each, and explain what additional resource would actually change delivered output. Keep a service measure alongside any cost or value measure. State whether the choice maximizes value, protects a commitment, or reduces the worst shortfall. A different goal can produce a different sensible answer from the same facts. Finish by testing one deliberately wrong proposal, such as a receipt used before arrival or a quantity above a resource ceiling. Your table should make that error visible. Save the rejected proposal with a short explanation, because it teaches a reviewer how the checks work. The eight hours include rebuilding, scenario work, writing, and teach-back; they are self-paced estimates rather than measured completion times. Faster readers should deepen the checks instead of merely rereading the text.

  1. Define units and dates
  2. Calculate required use
  3. Check every limit
  4. Compare actions
  5. Release a conditional plan
A promise follows the checks; it does not replace them.
FICTIONAL WORKED EXAMPLE

Northstar: recovery scenarios and uncertainty

All quantities below are fictional and apply only to this fully specified exercise. Monetary values are generic currency units.

ScenarioAssumed probabilitySupplier ceilingMake ceilingShipping ceiling
Nominal0.6243230
Shipping downside0.4243227
  1. 1. Add five supplier equivalents: supply becomes 29 at cost 50.
  2. 2. Downside flow remains 27, leaving 2 bottles late.
  3. 3. Contingent backup costs 0.4×18 = 7.2 expected currency units and closes that modeled gap.

Supplier recovery plus a reliably available contingent carrier clears both modeled scenarios for expected cost 57.2.

Assumptions

  • All unlisted resource restrictions are absent for this teaching case.
  • Use the timing, yield, and carry rules stated in the lesson; do not add unstated receipts.

Where this can fail: This model is conditional on its supplied inputs. It does not certify supplier execution, actual yield, or a detailed shop-floor sequence.

TRY IT YOURSELF · 8-HOUR ACTIVITY BUDGET

Build, test and explain a plan

Build a two-period scenario table. Each period requires 29 good bottles and has baseline ceilings supplier24/make32/ship30, with no carry. In period two downside shipping is 27. Compare no action; buy five supplier equivalents each period at 10 each; buy those plus a guaranteed backup reservation costing 6 upfront and 18 only if used. The reservation adds three slots in the downside. Assume downside probability 40% and the reservation is the only way to ensure access. The eight-hour estimate covers an original workbook or paper model, scenario calculations, checks, and communication; it is not experimentally validated.

Use paper or a spreadsheet. The estimates below include the study and worked example already on this page.

Estimated hoursActivity
0.5Study the two constraint explanations. Write a data dictionary with units, dates, and the boundary of each resource.
0.5Recalculate the worked example without looking at its answer. Reconcile every difference and record the corrected arithmetic.
3Build the complete multi-period or multi-case planning table specified above. Keep inputs separate, show all formulas, and add explicit checks for capacity, stock, and due quantities.
2Run every requested stress case. Add a comparison table of resource use, feasible output, remaining gaps, and the first constraint that blocks improvement.
1Write a one-page decision memo that selects a feasible action, states its goal, names the assumptions, and distinguishes firm results from conditional ones.
1Teach the model aloud to an imagined colleague. Trace one bottle or one decision through all rows, test one invalid proposal, and revise unclear labels.

Your deliverables

  • A reproducible planning table with inputs, formulas, units, and checks.
  • A scenario comparison with service and resource consequences.
  • A decision memo and short teach-back outline.
Check your practice work
  • No action yields five short each period, ten total, in either shipping scenario.
  • Supplier recovery costs 100 and yields total shortfall 0 nominal or 2 downside; expected shortfall is 0.8.
  • Reserved backup policy costs 106 nominal or 124 downside; expected cost 113.2 and modeled shortfall 0 in both.
  • The 6 reservation fee is paid in both outcomes; the 18 activation fee is paid only in downside.

Keep these three ideas

  • Evaluate recovery as a chain of contingent effects.
  • Keep quantities, resource units, and due times explicit.
  • Recheck all constraints after a change, and report remaining uncertainty.

Common mistakes

  • Treating capacity in a later time bucket as available before the due gate.
  • Calling an expected or conditional quantity a guaranteed shipment.

Optional video study

Evaluate recovery as a chain of contingent effects.

  • Frame the Northstar constraint and unit.
  • Walk the checked example through every resource.
  • Compare the lab stress cases and explain the release decision.

The first half of the module narration uses this lesson’s case and checks.

Open the module media & quiz

Put this idea to use

Carry your assumptions into a practical tool, then compare your result with a short guide.