MODULE 05 · 19 ESTIMATED HOURS

The five-track operating capstone

Connect the full planning chain to a conditional release and execution feedback.

LESSON 1 · 8-HOUR ACTIVITY PLANJoin five planning tracks into one release

Trace demand through stock, supply, constraints, and a dated production release.

LESSON 2 · 8-HOUR ACTIVITY PLANRun the end-to-end operating review

Issue a reviewable release package and feedback loop for the five-track plan.

Watch, listen or read

Connect the full planning chain to a conditional release and execution feedback.

5:33 · Original narrated lesson slides. AI-generated narration through Runway; factual diagrams assembled for this course. Video is optional. The complete transcript is directly below.

Read the complete narration transcript

A detailed schedule is the last handoff in a much longer plan. It cannot fix a demand count that is wrong, stock that is not usable, or input that will not arrive. The final Northstar case joins five tracks. We count demand, reconcile inventory, check supply, test the constraint, and place work on a clock. Each track must use the same week and the same units. When the facts do not match, stop and show the gap before releasing the work. Next week demand is fifty one bottles. There are six more from old backlog. Usable stock is eighteen and a receipt of ten arrives before demand. Add fifty one and six, then subtract eighteen and ten. The net new need is twenty nine. The backlog is separate in this case. If a forecast already holds a current order, do not add that order a second time. A clean demand count is the first step toward a credible job quantity. Now check the original supply path. Supplier availability is twenty four, the manufacturing limit is thirty two, and shipping can support thirty. These are good unit equivalents for the same week. The path is limited to twenty four, leaving five of the twenty nine uncovered. A clever job order cannot create the missing supply. Keep this base gap on the record. It explains why a recovery decision is needed before the detailed schedule can support the full new requirement. For a separate approved recovery, thirty physical input units are ready at the start of the shift. Each permits one bottle start. Expected yield is ninety seven percent. Thirty starts give twenty nine point one expected good bottles. We round the start plan up from twenty nine divided by the yield. But expected is not guaranteed. A batch can return fewer good bottles. The shipment plan needs an actual accepted count, not just a fraction multiplied by the number started. Each start takes twelve minutes, so thirty starts use three hundred sixty run minutes. Add one thirty minute setup to get three hundred ninety minutes of filler load. The usable shift is four hundred eighty, leaving ninety minutes of filler headroom. Setup runs from zero to thirty and filling from thirty to three hundred ninety. This is a time check under the recovered input assumption. It is not evidence that the original five bottle supply gap disappeared on its own. The route still has two steps. A separate inspector needs thirty minutes for the whole lot after filling. Packing then needs thirty minutes on its own station. Inspection ends at four hundred twenty and packing at four hundred fifty. The shipping cutoff is four hundred eighty. Route slack is thirty minutes, not ninety. The filler can be free while the lot still waits on later steps. Use the final route finish when you check the shipping promise. Test three facts one by one. If input is forty five minutes late and setup must wait for it, packing ends at four hundred ninety five. The cutoff is missed by fifteen. If each start instead takes thirteen minutes, the base route ends right at four hundred eighty. If actual good output is only twenty eight, total usable supply is fifty six against a need of fifty seven. The time plan can succeed while the quantity plan still misses one bottle. Close the review with a record a colleague can follow. State the demand count, usable stock, input recovery, start quantity, resource times, accepted output gate, and shipping cutoff. Send a late receipt back to supply planning, a yield loss back to the quantity balance, and a run time change back to the capacity check. Do not ask the scheduler to cure every gap by moving bars. A good release joins the five tracks and makes the next decision clear when the actual result differs from the plan. Use the same discipline for the next review. Record what was assumed and what was observed. Thirty starts and twenty eight accepted bottles are two distinct facts, and both belong in the record. Do not overwrite the planned yield with the actual count or erase the original need. Those facts explain why a gap exists and help the next team choose a response. A release is strongest when it gives people both a plan to follow and a clear way to report that the plan no longer fits.

Video teaching plan
  1. Reconcile demand

    Original static calculation card for reconcile demand, using the Northstar numbers stated in the narration; show labeled units and no decorative charts.

    • 51 demand plus6 backlog
    • Stock18 and receipt10
    • Net new need29
  2. Expose the supply gap

    Original static timeline for expose the supply gap, using the Northstar numbers stated in the narration; show labeled units and no decorative charts.

    • Limits24,32,30
    • Original ceiling24
    • Five-unit gap
  3. Size conditional starts

    Original static calculation card for size conditional starts, using the Northstar numbers stated in the narration; show labeled units and no decorative charts.

    • 30 recovered inputs
    • 30 starts at97% yield
    • 29.1 expected good
  4. Build the full route

    Original static timeline for build the full route, using the Northstar numbers stated in the narration; show labeled units and no decorative charts.

    • Filler ends390
    • Inspect to420
    • Pack to450
  5. Test actual output

    Original static timeline for test actual output, using the Northstar numbers stated in the narration; show labeled units and no decorative charts.

    • Cutoff480
    • Accepted28 leaves gap1
    • Yield is not a guarantee
  6. Close the five handoffs

    Original static calculation card for close the five handoffs, using the Northstar numbers stated in the narration; show labeled units and no decorative charts.

    • Demand and inventory agree
    • Supply and constraint checks
    • Schedule feeds back actuals
PUT IT TOGETHER · 2 HOURS

Module practice & recap

Northstar week: demand51, separate backlog6, usable stock18, receipt10 before demand. Original same-week finished-good-equivalent limits supplier24, manufacturing32, shipping30. Approved recovery provides30 physical start inputs at0. Yield97%, run12 minutes/start, setup30, filler open0-480. Whole-lot inspection30 then packing30 use separate resources open0-480. Shipping cutoff480; transfer0. Accepted output is measured, not guaranteed.

  1. Reconcile demand and inventory and show the original five-unit supply gap separately from the recovered-input plan.
  2. Build the recovered route for30 starts and distinguish expected good output from acceptance evidence.
  3. Test input release45 with setup waiting for inputs, and separately actual accepted28. Show time and quantity effects independently.
  4. Prepare a five-track handoff record, a conditional dispatch instruction, and a decision on whether the original promise can be confirmed in each scenario.

What to produce

Ordinary practice answer checks
  • Net requirement29; original flow ceiling24; uncovered5. Recovery is a changed supply assumption, not a sequencing gain.
  • 30 starts imply29.1 expected good, load390, filler headroom90. Inspect390-420, pack420-450; cutoff slack30.
  • Release45 gives pack completion495, missing cutoff15. Actual accepted28 with base timing gives total supply56 versus57 demand-plus-backlog, leaving1 unfilled.
  • A firm promise requires accepted quantity and a feasible shipping plan; neither expected yield nor filler headroom alone proves it.
CHECK YOUR UNDERSTANDING

10 quick questions

Choose an answer, then check it. Retry any question without penalty. The one-hour budget includes checking, revisiting examples, and explaining your choices.

0 of 10 answered · 0 correct

1. Demand 51 plus separate backlog 6 less stock 18 less receipt 10 gives?
2. Limits supplier 24, manufacturing 32, shipping 30 give flow ceiling?
3. Net need 29 and original flow ceiling 24 give shortfall?
4. At 97% expected yield, starts to cover 29 on expectation are?
5. Thirty starts at 97% yield mean?
6. Thirty starts×12 minutes plus 30 setup gives load?
7. Usable shift 480 less filler load 390 gives?
8. Filling ends 390, inspection 30, packing 30. Packing ends?
9. Accepted 28 plus stock 18 plus receipt 10 versus total need 57 leaves?
10. Input delay 45 shifts whole 450-minute route. Against cutoff 480, delay is?