Example SCI-011: Transfer stock on the wrong side — Inter-site stock is unavailable until transfer receipt.
What goes wrong: A transfer delay creates local backlog despite network sufficiency. How we fix it: Preposition the specified buffer before the first demand day.
Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.
Visual Before-and-After Chart (SCI-011)
Key Question to Ask: Distinguish network stock from local usable stock at the serving site.
How to Fix It: Preposition the specified buffer before the first demand day.
Simple Summary of This Example
- Example Number:
SCI-011(spare parts) - Plain-English Topic: Why Having Enough Weekly Stock Still Fails If Delivery Arrives One Day Late
- Main Goal: maximize due-date fulfillment
- Important Limit: Five demand days; FIFO backlog; no lost sales.
Starting Numbers & Units for SCI-011
| Number Name | Unit of Measure | Starting Value | Allowed Range |
|---|---|---|---|
opening stock (opening_stock) |
pieces | 150 | 0 to 1000000 (integer) |
daily demand (daily_demand) |
pieces | 100 | 0 to 1000000 (integer) |
receipt quantity (receipt_quantity) |
pieces | 400 | 0 to 1000000 (integer) |
receipt day (receipt_day) |
ordinal calendar day with day one Monday | 2 | 0 to 1000000 (integer) |
delay days (delay_days) |
calendar days | 1 | 0 to 1000000 (integer) |
buffer units (buffer_units) |
pieces | 50 | 0 to 1000000 (integer) |
Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-011)
| Result Name | Unit | Normal Day (Baseline) | Problem Day (Stress) | Fixed Plan (Repair) |
|---|---|---|---|---|
on time units (on_time_units) |
pieces | 500 | 450 | 500 |
late units (late_units) |
pieces | 0 | 50 | 0 |
ending stock (ending_stock) |
pieces | 50 | 50 | 100 |
ending backlog (ending_backlog) |
pieces | 0 | 0 | 0 |
peak backlog (peak_backlog) |
pieces | 0 | 50 | 0 |
Other Related Examples on "Why Having Enough Weekly Stock Still Fails If Delivery Arrives One Day Late"
- SCI-008: Receipt after the daily promise — One receipt moves past Tuesday demand.
- SCI-009: Inspection before usable receipt — An arriving shipment waits for inspection.
- SCI-010: Delivery after customer opening — The customer opens before the truck arrives.
- SCI-011: Transfer stock on the wrong side (This Page)
- SCI-012: Weekend receiving gap — The dock cannot receive on the planned day.
- SCI-013: Late kit staging — Material arrives after the assembly staging window.
- SCI-014: Supplier confirmation moved — The latest accepted confirmation is one day later.