Supply Chain Ideas Simple, Clear Supply Chain Learning for Everyone
WORKED SUPPLY CHAIN EXAMPLE · SCI-012 · PRINTED MATERIALS

Example SCI-012: Weekend receiving gap — The dock cannot receive on the planned day.

What goes wrong: The next usable receipt date is later than its transport arrival. How we fix it: Preposition the specified buffer before the first demand day.

Everyday Real-Life Example: Common mistake: thinking "Enough end-of-week supply means every order is on time." In reality: A receipt crosses a due-date boundary while total supply stays equal.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-012)

Bar chart comparing normal day, problem day, and fixed plan for SCI-012

Key Question to Ask: Confirm the receiving calendar used by the availability promise.

How to Fix It: Preposition the specified buffer before the first demand day.

Simple Summary of This Example

Starting Numbers & Units for SCI-012

Starting Numbers and Allowed Ranges (SCI-012)
Number Name Unit of Measure Starting Value Allowed Range
opening stock (opening_stock) pieces 150 0 to 1000000 (integer)
daily demand (daily_demand) pieces 100 0 to 1000000 (integer)
receipt quantity (receipt_quantity) pieces 400 0 to 1000000 (integer)
receipt day (receipt_day) ordinal calendar day with day one Monday 2 0 to 1000000 (integer)
delay days (delay_days) calendar days 2 0 to 1000000 (integer)
buffer units (buffer_units) pieces 150 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-012)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
on time units (on_time_units) pieces 500 350 500
late units (late_units) pieces 0 150 0
ending stock (ending_stock) pieces 50 50 200
ending backlog (ending_backlog) pieces 0 0 0
peak backlog (peak_backlog) pieces 0 150 0

Other Related Examples on "Why Having Enough Weekly Stock Still Fails If Delivery Arrives One Day Late"