WORKED SUPPLY CHAIN EXAMPLE · SCI-072 · PROMOTIONAL GOODS

Example SCI-072: Campaign launches early — A campaign begins before the approved calendar.

What goes wrong: Early demand consumes buffer before the scheduled receipt pattern. How we fix it: Preposition the declared buffer before period one begins.

Everyday Real-Life Example: Common mistake: thinking "An accurate horizon total guarantees the right inventory timing." In reality: Demand shifts earlier while the four-period total stays fixed.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-072)

Bar chart comparing normal day, problem day, and fixed plan for SCI-072

Key Question to Ask: Check whether the launch date changed after supply was planned.

How to Fix It: Preposition the declared buffer before period one begins.

Simple Summary of This Example

Starting Numbers & Units for SCI-072

Starting Numbers and Allowed Ranges (SCI-072)
Number Name Unit of Measure Starting Value Allowed Range
opening stock (opening_stock) pieces 20 0 to 1000000 (integer)
receipt per period (receipt_per_period) pieces 100 0 to 1000000 (integer)
base demand (base_demand) pieces 100 0 to 1000000 (integer)
pull forward (pull_forward) pieces 80 0 to 1000000 (integer)
extra buffer (extra_buffer) pieces 60 0 to 1000000 (integer)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-072)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
on time units (on_time_units) pieces 400 220 400
late units (late_units) pieces 0 180 0
ending stock (ending_stock) pieces 20 20 80
peak backlog (peak_backlog) pieces 0 60 0