Example SCI-090: Rounding at the wrong stage — Fractional good units are not shippable.

What goes wrong: A fractional intermediate cannot satisfy a whole customer unit. How we fix it: Stage enough input before processing at the same lower yield.

Everyday Real-Life Example: Common mistake: thinking "Planned input units equal shippable output units." In reality: A lower yield creates output shortage from unchanged input.

Interactive calculator loads automatically in modern browsers. All plain-English explanations, units, and tables are shown directly on this page.

Visual Before-and-After Chart (SCI-090)

Bar chart comparing normal day, problem day, and fixed plan for SCI-090

Key Question to Ask: Floor physical output before calculating delivered units.

How to Fix It: Stage enough input before processing at the same lower yield.

Simple Summary of This Example

Starting Numbers & Units for SCI-090

Starting Numbers and Allowed Ranges (SCI-090)
Number Name Unit of Measure Starting Value Allowed Range
demand units (demand_units) pieces 90 0 to 1000000 (integer)
planned input (planned_input) pieces 100 0 to 1000000 (integer)
baseline yield percent (baseline_yield_percent) percent from zero to one hundred 95 0 to 100 (number)
stress yield percent (stress_yield_percent) percent from zero to one hundred 89 1 to 100 (number)

Compare Normal Day vs. Problem Day vs. Fixed Plan (SCI-090)

Results for Normal Day (Baseline), Problem Day (Stress), and Fixed Plan (Repair)
Result Name Unit Normal Day (Baseline) Problem Day (Stress) Fixed Plan (Repair)
good units (good_units) pieces 95 89 90
on time units (on_time_units) pieces 90 89 90
late units (late_units) pieces 0 1 0
processed units (processed_units) pieces 100 100 102