Netting and time
Reconcile unique demand, usable supply, and dated carry-forward balances.
Reconcile forecast, orders, backlog, and usable supply before proposing a purchase.
LESSON 2 · 8-HOUR ACTIVITY PLANTime the receipts, then carry the balanceBuild dated balances and show how late receipts change service even when totals match.
Watch, listen or read
Reconcile unique demand, usable supply, and dated carry-forward balances.
4:56 · Original narrated lesson slides. AI-generated narration through Runway; factual diagrams assembled for this course. Video is optional. The complete transcript is directly below.
Read the complete narration transcript
A supply plan starts with a simple question. What must be ready, where, and when? It does not start with a new order. First, we need to know what the demand means. Then we need to know which stock can serve it. Northstar makes reusable bottles. Its next week total is fifty one bottles. Twenty of those are firm orders. The other thirty one are still forecast demand. We do not add twenty to fifty one. The twenty are already in that total.
Now add a fact from last week. Six bottles are still owed to customers. Those six are not in the new total. They are a backlog. So the need we must cover is fifty seven. That small word, separate, does real work here. If the fifty one already held the old six, adding them again would be wrong. Good plans show the rule beside the number. They do not leave it in one person's head.
Northstar has eighteen usable bottles on hand. Ten more will be ready before the need. Eighteen plus ten gives twenty eight units of supply. Fifty seven less twenty eight leaves twenty nine. That is the net need. It is a request for more supply. It is not proof that a source can fill it. Keep the need and the firm supply in two fields. This makes the gap clear and keeps hope out of the promise.
What counts as usable? A bottle held for a quality check may be in the building but not ready to ship. A bottle in the wrong place may miss the truck. An open order may be real but late. We need both a status and a date. When an order moves from planned to firm, change its status. Do not add a second copy of the same ten bottles. The plan should follow the goods, not count each new message as more goods.
Now change just one fact. All fifty seven bottles are due on Tuesday, but the ten unit receipt is ready on Friday. At the Tuesday event, Northstar has only eighteen. The gap is thirty nine. At the end of the week, the total gap may still look like twenty nine. Both views can be true. One tells us the final balance. The other tells us who waits. This is why we split a week into days when a close date matters.
There are two sound ways to carry a shortage. In a signed view, the balance can go below zero. That is a signal, not real negative stock. In a physical view, stock stops at zero and the unmet need becomes backlog. Use one method at a time. If you carry a negative balance and also subtract that same backlog next day, you count the gap twice.
Try a small check. Start Monday with eight bottles and demand for twelve. Ship eight. End with zero stock and four backlog. On Tuesday, ten bottles arrive before six new units are due. Use four for the old need and six for the new need. Both stock and backlog end at zero. The signed view starts Tuesday at minus four, adds ten, and takes away six. It also ends at zero. The two views agree.
Your lab builds both views for five days. Do not just copy a formula down a column. Trace which due date each shipment serves. Then move a receipt to a later day. Ask whether final backlog changes, whether on time service changes, and whether both measures tell the same story. A plan can end at the same balance yet serve fewer units on time.
Before you hand over the result, read each total as a sentence. Say what the units are, whose need is included, and when the goods can be used. Check that each order appears once. Keep old due dates when goods are late. These habits make a short table a useful shared record. They also make errors easier to find before a buyer spends money or a customer gets a promise that the chain cannot meet.
Here is one final test to say aloud. If three opening bottles fail a check, how much does the net need rise? It rises by three, from twenty nine to thirty two. The demand did not change. Eligible supply changed.
Video teaching plan
- One population
Two blocks inside one fifty-one-unit demand bar
- 20 confirmed
- 31 residual
- No duplicate
- Separate old need
Backlog joins the new-demand bar
- 51 new
- 6 overdue
- 57 total
- Eligible supply
Stock and timely receipt reduce a need bar
- 18 stock
- 10 receipt
- 29 net
- Date matters
Tuesday need appears before Friday receipt
- Tuesday cutoff
- Friday arrival
- 39 event gap
- Two ledgers
Signed and physical balance cards reconcile
- Negative signal
- Stock stays zero
- Backlog separate
- Audit the handoff
Five-day ledger with a late-receipt marker
- Trace each ID
- Keep due date
- Explain service
Module practice & recap
Reconcile a week without hiding its Tuesday gap. Northstar has total next-week demand 51 including 20 confirmed orders, separate backlog 6, and 18 usable opening units. Demand occurs Tuesday. A ten-unit receipt becomes usable Friday. A confirmed alternate can supply up to 39 units before Tuesday at a $2/unit premium. No safety-stock target; excess may remain Friday. Suggested time: one hour model and checks, one hour scenarios, one hour memo and peer-style review; estimates are not experimentally validated.
- Create a unique-demand bridge showing confirmed and residual forecast.
- Build Tuesday and Friday event balances under no alternate, alternate 29, and alternate 39.
- Compare original-date service with week-end stock and backlog.
- Write a three-hour review memo recommending a quantity and explaining the cost/service tradeoff.
What to produce
- A reconciled scenario table with formulas and units.
- A short decision memo with service, cost, and risk implications.
- An assumption and exception register with owners and review dates.
Ordinary practice answer checks
- Total demand 57, not 77. Tuesday supply gap 39.
- Alternate 29 allows Tuesday shipments 47, leaving ten late; Friday receipt clears them and stock ends zero.
- Alternate 39 allows all 57 Tuesday and leaves ten stock Friday. Premiums are$58 versus$78; final choice depends on value of on-time service and excess stock.
10 quick questions
Choose an answer, then check it. Retry any question without penalty. The one-hour budget includes checking, revisiting examples, and explaining your choices.
0 of 10 answered · 0 correct